Its been how long??
11/01/2009
Its been about a month now since settlement on the house.
It seems like it was so long ago. We have spent so much time at the house and it still feels like there is so much to do.
3 weeks off work, every day spent at the house. I go back to work on Monday, so things will go even slower.
So far the items complete include
- Asbestos removed
- Laundry floor pulled up
- Bathroom, toilet and laundry ripped out
- Installed all the floors and plastered in the toilet
- Installed all walls in the laundry
- Installed 90% of the walls in the bathroom
- Tiled 90% of the laundry, toilet and hallway floor
- Painted the Office and Master Bedroom
- Painted the undercoat of the Master Bedroom floor
- Plumbing done
- Power points and light switches replaced
Things to be done
- Finish the bathroom walls and plaster
- Paint the toilet
- Install the toilet, this should be done by tomorrow afternoon.
- Put the bathroom floor tiles in and tile all the walls
- Paint the Master Bedroom floor and the Office floor
- Get electrician to install down lights in bathroom and lounge room
- Install network and phone cabling
- Dig trench and install storm water pipes
- Paint toilet, laundry and hallway walls
- Paint bath
- Install bathroom cabinet with sink
- Install shower screen
- Build/install cabinets and desk for Office
- Get a built in wardrobe for Master Bedroom
Oh! and,, MOVE IN!!
I think thats all for now. Please excuse me while I go and collapse..